    "桐乡市市级领导联系重点攻坚项目进展情况表(2009年1-7月份)"
    "单位:万元"
    "市级联 系领导","项目名称","项目类型","计划投资情况",,"09年累计投资数",,"09年累计完成财务数","形象进度"
    ,,,"总投资","09年 投资","完成数","完成 比例%"
    "费建文","浙江五丰电缆有限公司","工业",6500,6500,3000,"46.15 ",3000,"厂房基建已开始"
    ,"桐昆集团浙江恒通化纤有限公司40万吨 熔体直纺项目","工业",120000,68600,42883,"62.5 ",35992,"6月23日投料生产聚酯切片,7月6日生产涤纶差别化长丝, 现整个生产流水线畅通,生产负荷达100%,目前产销基本平 衡."
    ,"革新区块开发建设","基础设施",110000,30000,10980,"36.6 ",10980,"区块规划调整策划正在进行中;农居点规划方案完善,村民 组成片苗木丈量."
    "朱海平","巨石集团有限公司","工业",100000,100000,90550,"90.5 ",90551,"厂房面积90000平方竣工,已投入使用."
    ,"振石集团华美复合材料有限公司","工业","5000 ","5000 ",3601,"72.0 ",3601,"面积50000平方的厂房竣工,已投入使用."
    ,"振石集团恒石纤维纤基业有限公司","工业",10000,10000,4500,45,3082,"约50000平方厂房基本竣工,已投入使用.."
    ,"桐乡市污水处理尾水外排工程","基础设施",97145,41400,32552,"78.6 ",18336,"管网埋设27635米,占计划的79.8%;崇福出口泵完成工程量 的48%;6号泵站沉井完成工程量的40%;7号泵站沉井完成工 程量的35%.排江口工程埋设管道1.427公里,完成陆域管线 工程量的97%,高位井完成标高-19.5至-5.5米浇筑,已下沉 22米,占工程量的70%."
    "顾政宇","浙江欧图纺织有限公司","工业",8000,2500,4100,164,4100,"一期厂房完工并投产,综合楼结顶装修."
    ,"嘉兴丹顶鹤服饰有限公司","工业",5200,1200,1975,"164.6 ",1975,"主厂房结顶,进入后期施工及装修阶段."
    ,"中国毛衫城","服务业",14700,7700,9257,"120.2 ",6386,"五层浇筑并结顶,进入外部装修."
    "池晓明","嘉兴永发电子不锈钢金属制品项目","工业",9200,2000,1700,85,1700,"已完成消防,规划验收,进入全面生产阶段.附属工程已经 完成."
    ,"新凤鸣集团股份有限公司36万吨熔体直纺 项目","工业",97800,20000,1460,7.3,1460,"主要聚酯设备供应商确实,商务谈判结束;所涉276亩土地 挂牌,已进入推土阶段,河岸,道路近期开工."
    ,"洲泉四星宾馆","服务业",10000,5000,,,,"正在重新建筑设计"
    "沈海明","浙江中游康体设备有限公司年产15万件 康体游乐设备","工业",7000,2000,827,41.3,377,"现在装修基本完成,准备投入设备."
    ,"浙江宝妮羊绒有限公司年产30万件羊绒衫 项目","工业",5000,2500,,,,"项目已摘牌,规划设计正在进行中."
    ,"桐乡振石大酒店","服务业",50000,15000,7785,"51.9 ",7785,"完成地下室至±0.000部分的砼浇筑,附楼1完成二层楼面浇 筑,完成主楼±0.000以下的砼浇筑."
    "张林洪","上海海德控制系统股份有限公司","工业",8000,4000,1500,37.5,1190,"1#厂房部分建成投入使用,二幢宿舍主体完成,2#厂房建 至二楼.生产用电已接通."
    ,"固耐重工(嘉兴)有限公司","工业",30000,5000,3000,60,2664,"一期二幢车间基础通过验收,二幢研发楼主体完工,能评待 论证."
    ,"东宗线航道嘉兴段二期工程","基础设施",32320,5000,2367,"47.3 ",1550,"航道1合同段已累计完成开挖水上土方128.8万方;校场路桥 累计完成灌注桩76根,立柱52根,承台2个,盖梁14块,预 制梁板288片,16个箱梁节段,护栏240m;环城南路桥累计 完成灌注桩64根,梁板累计完成233片,立柱59根,盖梁24 片,承台2个."